January 22, — News

How Long Does It Take to Strip Powder Coating and E-Coat? A Complete Guide

One of the most common questions we hear from manufacturers, powder coaters, and industrial finishers is: 
“How long does it take to strip powder coating or e-coat using Greensolv solutions?” 

The short answer: 
Anywhere from 30 minutes to several hours, depending on coating thickness, layers, temperature, and bath cleanliness. 

Here’s a clear breakdown to help you plan production cycles more efficiently. 

Standard Powder Coatings & E-Coats: 30–60 Minutes 

Using Greensolv’s three precision-formulated immersion stripping solutions— 

  • SteelStrip 

  • AlumiStrip 

  • AeroStrip 

standard powder coatings and typical e-coats are fully removed in: 

 30 to 60 minutes at 185°F (85°C) 

This timing applies to most common industrial coatings, making Greensolv’s solutions an ideal choice for fast turnaround and consistent results. 

Multi-Layer Coating Systems: Up to 2 Hours 

If your parts have a layered system consisting of: 

  • Primer 

  • Top coat 

  • Clear coat 

…expect a longer dwell time. 

 Up to 2 hours for a full clean removal 

Multi-layer systems take more time because each layer has different hardness characteristics and chemical resistance levels.  

Stubborn or High-Performance Coatings: 4–8 Hours 

Some coatings simply take more time, such as: 

  • High-durability architectural coatings 

  • Industrial primers designed to resist chemical attack 

  • Thick automotive layers 

  • Burned-on or aged coatings 

For these tough systems: 

 Plan 4–8 hours for complete stripping 

These long cycles are typically done overnight to optimize workflow. 

How Many Batches Can You Strip Per Day? 

When planning your production schedule, here’s a helpful benchmark: 

2-hour cycle = 5 batches per day 

During a standard 8-hour shift, you can typically run: 

  • 4 batches during the workday 

  • +1 overnight batch for maximum efficiency 

This keeps your workflow predictable and helps you plan throughput with confidence. 

Temperature: Your Most Important Efficiency Lever 

Stripping speed is highly temperature-dependent. 

A simple rule of thumb: 

A 20°F (≈11°C) temperature increase cuts stripping time in half. 

Example: 

  • 165°F = 2-hour strip time 

  • 185°F = 1-hour strip time 

Maintaining the recommended temperature is one of the easiest ways to improve productivity without changing chemistry.  

Solution Cleanliness Matters 

Hot-bath immersion stripping is extremely reliable, but only if your solution is well maintained. 

A clean, well-filtered bath ensures: 

  • Faster and more predictable stripping times 

  • Less sludge buildup 

  • Longer solution life 

  • Consistent batch-to-batch performance 

Regular maintenance maximizes chemical efficiency and keeps your production running smoothly.  

Reliable, Predictable, and Efficient Paint Stripping 

Whether you’re removing powder coating, e-coat, or multilayer systems, Greensolv’s chemical stripping solutions deliver: 

  • Fast cycle times 

  • Consistent results 

  • Predictable scheduling 

  • Lower labor requirements compared to blasting or sanding 

If you’re aiming to increase throughput or streamline your stripping process, Greensolv can help. 